IESO Clarkson – SCADA Replacement
Design-build for the IESO headquarters
01 · Problem An outdated SCADA system
The BMD and Mohawk team was the selected service provider for deploying and executing a complete design-build initiative to commission a new SCADA system that would replace the existing SCADA monitoring infrastructure for the IESO's Headquarters, powering the IESO Control Room.
The team selected and designed a solution that uses Inductive Automation Ignition SCADA based on a comprehensive analysis of the IESO's specific requirements. This includes a single I/O nodes to consolidate the functions of the existing gateway from I/O boxes into modular nodes; redundant servers, configured as a warm-standby redundant pair; upgraded HMI that retains established single-line diagram, alarms and events, equipment status, and control workflows, while adding room-level detail, dynamic electrical section coloring, historical trends, and customizable charts; and cybersecurity and recovery provisions.
A comprehensive implementation plan was developed, including pre-commissioning off-site setup and testing at Mohawk's lab facility to reduce installation troubleshooting and minimize commissioning downtime. The upgrade is intended to preserve existing monitoring and control functionality while improving system maintainability, operator visibility, and recovery capabilities.
02 · Approach Ignition Perspective, fed by the RTAC
- I led the HMI design and built the application in Ignition 8.3 Perspective.
- Data comes in from an SEL RTAC over DNP3 and drives single-line diagram displays with breaker control, alarming, a sequence-of-events log and historian trend charts.
- Role-based access and audit logging; a shared SOE logging library; dynamic historian charts.
- Redundant master/backup gateways with SQL Server historian storage.
03 · Stack What it runs on
HMI Ignition 8.3 Perspective Field controller SEL RTAC Protocols DNP3 · OPC UA Historian SQL Server Redundancy Master / backup gateway pair - HMI
- ALM
- SYNC
- HIS
- PRO
- FLD
04 · Outcome Commissioning
COMMISSIONINGDesign phase completed
- Client
- IESO
- My role
- HMI design lead
- Platform
- Ignition 8.3 Perspective
- Data source
- SEL RTAC
- Protocols
- DNP3 · OPC UA
- Historian
- SQL Server
- Status
- COMMISSIONING